Briefing 76 - May 1995
print this page
76.1 NEW HOPE FOR DOUNREAY REPROCESSING PLANT ?

There was new hope for the future of the D1204 research reactor 
reprocessing plant at Dounreay in April with confirmation that the US
 Government was considering using the plant to deal with thousands of 
Highly-Enriched Uranium (HEU) spent fuel elements.  The US Department 
of Energy has suggested using Dounreay to reprocess HEU fuel from 
overseas reactors as one possible option for dealing with some of the 
estimated 18,000 HEU spent fuel elements throughout the world.

The HEU fuel was originally supplied by the US to overseas reactors 
and the spent fuel returned to the United States. But in 1988 environmental 
concerns stopped the importation of spent fuel and Dounreay took over a 
relatively small but lucrative business reprocessing the HEU fuel for research 
reactors threatened with closure because of lack of storage space.

However, UK policy to return radioactive waste from reprocessing to the 
country of origin was unpopular with a number of countries and the US 
was opposed to reprocessing as it freed more weapons-grade material and 
also concerned that its policy of encouraging reactor operators to change 
from weapons-grade HEU fuel to low-enriched uranium would be 
undermined by the imports ban.  Also reprocessing was expensive 
and only considered as a last resort.

In August 1994 the US arranged an `emergency' shipment of 153 
spent HEU fuel elements from Austria, Sweden, Denmark and the 
Netherlands reactors facing closure from storage shortages. After 
lengthy legal action to try and stop the shipments because a proper 
environmental assessment had not been carried out, the fuel was eventually 
allowed into the US for storage at the highly polluted Savannah River plant 
in South Carolina.  The D1204 HEU plant at Dounreay was `mothballed' in 
August 1994 for lack of work as reactor operators hoped the US would renew 
importing their spent fuel.   

However, ministers and officials from the UK Department of Energy along 
with Dounreay have been strongly lobbying  the US Energy and State 
Departments for the Scottish plant to be used as part of a revised US 
non-proliferation policy.  The publication in March 1995 of a Draft 
Environmental Assessment (DOE/EIS-0218D) by the US Department of 
Energy shows their work has not been wasted.

The Draft EIS suggest three policy options: (a) importing all, or most of the 
HEU fuel into the US for storage (or possible reprocessing);(b) facilitate the 
storage or HEU fuel in the country of origin, with technical and financial support, 
or if this is not viable, support the reprocessing of the fuel at Dounreay (or 
possibly the Cogema plant at Marcoule in France);(c) a combination of the 
two options, with the US importing fuel from poorer countries or those 
considered greater proliferation threats, and Dounreay or France reprocessing 
fuel from western/developed countries.  Up to 10 years work could be 
available for Dounreay.

An additional problem highlighted in the Draft EIS is the waste from 
reprocessing.  Only some countries with nuclear power programmes have 
waste storage facilities for this high/intermediate level waste so the US would 
have to accept the waste from these countries if their fuel is reprocessed.  
Also any reprocessing of the HEU fuel, whether in the US, UK or France, 
will be strongly opposed by environmental and non-proliferation concerns.  
The US DoE is organising public meetings to discuss the Draft EIS and a 
final EIS is expected to be published in September.  

76.2. DOUNREAY'S WEAPONS LINKS

Despite often repeated official denials there was any link between operations 
at Dounreay and the UK's nuclear weapons programme more evidence has 
recently emerged to confirm direct links to the Atomic Weapons Establishment 
(AWE) at Aldermaston in England.

A special fast reactor fuel plant was built at Aldermaston as early as the 1960s 
to manufacture plutonium fuel for Dounreay's two fast reactors.  The existence 
of the plant was revealed recently in a report from the government's Advisory 
Committee on the Safety of Nuclear Installations (ACSNI).  The plant at the 
top-secret nuclear weapons factory is closed and a decommissioning contract 
will soon be awarded.

Last year UKAEA admitted that Dounreay had supplied weapons-grade 
Highly-Enriched Uranium (HEU) fuel for the Herald research reactor at 
Aldermaston used to simulate nuclear explosions and reprocessed its spent 
fuel for over 25 years until the reactor was closed in 1987.  An AWE 
spokesman said the Herald reactor "tested the effects of a simulated nuclear 
event on various materials used in the construction of warheads."
 (John O'Groat Journal 8.7.94)  He confirmed that the reprocessed 
HEU belonged to the Ministry of Defence.  

UKAEA weapons group operated the Aldermaston plant until 1973 
when the Ministry of Defence took over responsibility.  UKAEA also 
supplied the plutonium to Aldermaston from the Windscale (now Sellafield) 
site which it also operated. Warhead tests are now carried out in Aldermaston's 
Viper reactor.  Dounreay says it has not been directly involved in 
weapons work.

76.3. PLUTONIUM LEAK AFTER ACCIDENT

A major release of plutonium-239 dust into the atmosphere from 
Dounreay could have been much more serious in different weather 
conditions.  A south-easterly wind took the radioactive dust out to 
sea. A calm day would have deposited the dust over the plant, or a 
westerly wind would have taken it over the nearby town of Thurso.

The 20 megabecquerels of pu-239 was released after an accident on 
Saturday 11th February in the D1206 reprocessing building in the section 
handling recovered plutonium dust.  It is understood a "glove-box" pressurised 
and blew open ripping the seals.  The release amounted to about six months 
of routine pu-239 discharges from the plant, although only two percent of 
discharge limits.  Several workers have been tested for exposure to 
plutonium.

Workers at Dounreay are widely reported to be concerned that safety 
levels have dropped because of commercial pressures.  One worker 
commented: "This would not have happened five years ago.  Now its 
about how much money it costs when there is a shutdown."

76.4. NEW SUBMARINE COOLANT PLANT

The Trident nuclear submarine test reactor facility next to Dounreay, HMS 
Vulcan, is building a new UK£2.5m plant to treat radioactive coolant water 
from its PWR2 prototype pressurised water reactor after the two-year 
refuelling starts in 1996.  

Liquid waste from HMS Vulcan is discharged into the Pentland Firth via the 
Dounreay pipeline while intermediate and low level solid wastes is stored at 
either site.  Spent fuel from HMS Vulcan, like all submarine reactors, is not 
eprocessed but held in storage.

76.5. OTHER DOUNREAY NEWS

5.1. No more cancer studies: No further detailed Government studies are to be 
carried out into the increased level of leukaemia in children around Dounreay. 
Although monitoring of any new cases of cancer around Dounreay will continue, 
Government researchers have said future work should concentrate on existing 
studies on cancer cases around all UK nuclear sites.  A recent study around 
Dounreay found evidence of a new leukaemia cluster (See Briefing 75.3).

5.2. Cancer death link legal battles:  The widow of a former Dounreay worker 
is to continue her legal case alleging that her husband died after radiation 
xposure.  Mr Alex Gillen died of leukaemia in 1962 and was convinced an 
1959 incident while removing irradiated fuel from a reactor at Dounreay 
was responsible.  Dounreay says Mr Gillen's radiation film badge did not 
support his statements.  Meanwhile two women who had leukaemia when 
they lived near Dounreay have had to drop their legal claim for compensation. 
Legal aid support has been stopped for Mandy McVean and Sharon 
Coghill and they must now wait for new evidence if they are to continue 
their case.  Ms Coghill said: "I still believe that my illness was caused by 
Dounreay's activities...I do not believe for a minute that this was a co-incidence." 
(Press and Journal 18.1.95).

5.3. Help for Chernobyl: A UK£2.5m European Union contract to undertake 
a feasibility study into decommissioning the Chernobyl reactors, including 
further measures to protect the No 4 reactor which blew-up in April 1986, 
has been awarded to AEA Technology's commercial division - which is 
scheduled to be privatised in the near future. AEA Technology is also 
beginning decontamination work on the Bohunice A1 reactor in Slovakia 
following an accident in 1991. 

5.4. A good year ?: In 1993 reprocessing at Dounreay increased by 70 
per cent.  A total of 4.8 tonnes of fast reactor fuel and 2.5 tonnes of 
research reactor fuel were treated at the plant.

5.5. Staff lose safety review work: The contract to carry out safety 
reviews of operations at Dounreay has been won by Rolls Royce and 
Associates, the operators of the nearly Trident submarine facility, 
instead of the UKAEA's own staff.  

5.6. Plutonium to Sellafield: The 37th shipment of plutonium nitrate, 
recovered from reprocessing at Dounreay, was shipped from the nearby 
port of Scrabster in April to the Sellafield plant in north-west England.  
The plutonium was shipped on the European Shearwater, owned by 
Sellafield operators, BNFL, who took legal action to stop Greenpeace 
protesting against the shipment.

5.7. Big increase in plutonium discharges: Liquid discharges of plutonium 
241 from Dounreay increased 100-fold in 1993 compared to 1992.  
Atmospheric discharges also increased by over 20%.  In 1992 14 
gigabecquerels (0.3% of authorised limits) were discharged into the sea 
compared with 1,300 GBq in 1993 - nearly 9% of the limit. Air discharges 
increased from 1.2% of the limit in 1992 to 26% in 1993. The figures 
reflect a relatively quiet year for reprocessing in 1992 and the big increase 
in work in 1993.  Discharges are expected to increase further over the 
next 5-8 years.

76.6 WASTE SHIP'S WORLD TRIP

The first shipment of high-level radioactive waste from Europe to Japan left 
France on 23rd February and arrived in Japan two months later after a hugely 
controversial journey. The 14 tonnes of waste, produced from reprocessing 
Japanese spent fuel, was vitrified in 28 glass blocks and was the first of dozens 
of similar trips expected as the reprocessing wastes from Cogema's plant at 
La Hague and BNFL's Sellafield are returned to Japan and other overseas 
customers.

The waste was loaded in Cherbourg onto the BNFL ship Pacific Pintail, 
which took plutonium from France to Japan two years ago. The route
 taken was via Cape Horn and the Pacific, unlike the previous plutonium 
shipment which when via Africa and the Indian Ocean.  Numerous countries 
along the four or five potential routes, such as through either the Panama or 
Suez canals, either protested against the shipment or banned it from their 
territorial waters and Chile was among the countries to order the ship to 
change course and stay outside its waters.  The ship was shadowed 
throughout its journey by the Greenpeace ship Solo. 

76.7.  NEWS FROM SELLAFIELD

7.1. THORP contracts cancelled: Two German nuclear operators have paid 
UK£100m in compensation to cancelled reprocessing contracts at BNFL's 
THORP plant at Sellafield.  Changes in German law, which now allow 
storage of spent fuel, and the high cost of reprocessing convinced the 
operators cancellation of the contracts was worthwhile.  It remains to be 
seen if other operators follow. The contracts were for RWE's 
Gundremmingen and the Kruemmel reactor owned by KKK (GmbH).

7.2. Importing nitric acid: Over 180,000 gallons of contaminated nitric 
acid for the Sellafield reprocessing complex is to be imported into the 
UK from the United States.  The nitric acid, contaminated with uranium, 
is waste from the closed Hanford military reprocessing complex in the 
US and will be sent to the UK in up to 50 shipments. Operators, British 
Nuclear Fuels (BNFL) will put the acid through its Magnox reprocessing 
plant to separate out the uranium and then re-use the nitric acid in the same 
plant.  The deal means the US solves a major waste problem and BNFL 
needs less new nitric acid.

7.3. Ships not rail: BNFL has decided to increase shipments of European 
spent fuel direct to Sellafield's port of Barrow rather than rely on rail and 
ferry transport across the English Channel.  It is estimated that European 
shipments to Barrow will increase from an average of two to 60 a year. 
The re-named BNFL ship European Shearwater (See News in Brief) 
will be used for the shipments which began in October. BNFL said it had 
decided to use sea transport rather than rail and ferry because it needed a 
"secure alternative" because of doubts over the future of channel ferries, 
especially the Nord Pas de Calais which has been used for spent fuel 
shipments in recent years after environmental and union actions closed most  
other routes.  Environmental groups, in particular Greenpeace, have often 
disrupted both trains and ferries carrying spent fuel.  BNFL's new plans 
will make similar action much more difficult.

7.4. Irish court case: Legal action against Sellafield in Ireland by four 
residents of Dundalk has been allowed by the High Court in Dublin.  
The action claims pollution from Sellafield reaches the Irish coast 
causing health concerns.  They want the THORP reprocessing 
plant closed.

76.8. SCOTTISH NUCLEAR REVERSES WASTE POLICY

In a surprise about-turn, Scottish Nuclear (SN) has abandoned plans for 
dry storage of its spent fuel which it claimed would save it UK£45m a year. 
 Shortly after Environment Minister Mr John Gummer said the Government 
had no objections in principle to dry storage as an alternative to 
reprocessing - and just before its own plans for a dry store were 
expected to be approved - SN announced in February a new deal 
with BNFL for reprocessing and storing its fuel at Sellafield.  SN also 
sold the plans for the dry stores to BNFL who will now probably 
ensure they are never used.

Following the decision of two German nuclear operators to cancel contracts
with Sellafield (See above) BNFL were anxious to improve prospects for
 its new THORP reprocessing plant.  If SN had gone ahead with the dry 
stores it would have represented a severe blow to BNFL and reprocessing 
in general.  It now seems BNFL was desperate enough to offer SN such 
a cheap deal they could not refuse. Environmental concerns played little 
or no part in SN's commercial decision.  

The UK£4bn deal means THORP's order-book after 2005, which dropped 
to around 30% after the German cancellations, increases to about 40%.  
Under earlier contracts SN had already agreed to send 1,148 tonnes of 
spent fuel to Sellafield for reprocessing. Under the new deal a further 550 
tonnes will be reprocessed and another 1,044 tonnes will be stored at 
Sellafield until 2006 when a decision on whether to reprocess it will be 
made.

Meanwhile Nuclear Electric has signed a UK£14bn contract in April 
with BNFL to reprocess and manufacture fuel for its Magnox and advance 
gas-cooled reactors.  The contract is a re-negotiated deal with Nuclear 
Electric and represents a reduction of UK£100m in projected BNFL 
profits.

76.9. RESTRICTED INQUIRY INTO DUMP PLANS

A public inquiry in plans for a radioactive waste repository close to the 
Sellafield reprocessing plant in north-west England will begin in June.  
The government's nuclear waste disposal company NIREX plans a 
huge underground dump and wants to excavate an underground laboratory 
to test the geology of rocks and water-flow in the area.  The laboratory 
and dump is opposed by the local regional council and environmental 
groups whose demands for a full wide-ranging inquiry into all aspects 
of nuclear waste disposal has been rejected by the Government.  Instead 
there will be a local inquiry restricted solely to local planning matters.

A report by the Royal Society (an association of UK scientists) questioned 
the choice of Sellafield as the site of the UK underground  dump  for 
low-level radioactive  waste.   The report also recommended that the site 
should be extended westwards under the Irish Sea coast for dumping 
high-level waste, even though these wastes are excluded from the brief 
given to NIREX. Doubts were expressed about the geology of the area 
and the Royal Society said Sellafield was not the best choice except a 
political stand-point as there is likely to be less public opposition and 
no problem of land acquisition.

A report from geological consultants commissioned by Cumbria County 
Council has concluded that the East Anglia region of eastern England 
was a much better site for a nuclear waste dump.  Ground-water at the 
Sellafield site could be forced to the surface, the consultants believe.  
Another report published by NIREX last year shows that the geology 
of a site close to Dounreay was much more suitable than Sellafield.

76.10. SAFETY CONCERN AT NUCLEAR WEAPONS PLANTS

Serious safety concerns at the UK's four nuclear weapons production sites 
have been raised by the Health and Safety Executive (HSE).  "Serious 
inadequacies" in safety were found at the sites and they would have been 
refused a licence if they were not military establishments exempt from 
normal civil nuclear controls.

Standards were so poor HSE inspectors halted production of warheads 
for the Trident nuclear submarine programme and at another site inadequate 
precautions were being implemented to prevent a chain reaction. The nuclear 
weapons site are operated by a private company, Hunting-BRAE Limited, 
a consortium of Hunting plc, AEA Technology (the operators of Dounreay) 
and Brown and Root.  A number of enforcement orders were issued by 
HSE inspectors to rectify the plants' most serious omissions out of a 
list of 65 deficiencies.

76.11. SUPERPHENIX NOW EXPERIMENTAL REACTOR

After a four year shut-down due to of safety concerns, the Superphenix 
fast reactor in France was restarted last year as a `testing plant' for burning 
plutonium and other long-lived wastes. A six-year test programme has 
been approved at an estimated annual cost of UK£12m.  However, 
there are industry reports that the German, Belgium and Italian nuclear 
interests in Superphenix all want out of the expensive project.  If the 
experiment works it will be after 2000 before Superphenix produces 
more plutonium than it produces - and then it will consume only a 
small fraction of France's plutonium.

76.12. NEWS IN BRIEF

12.1. Nuclear - cancer link studies: A Health and Safety Executive study has 
concluded that there is not a link between a father's exposure to radiation at 
work and childhood leukaemia, undermining a 1990 report by the late 
Professor Martin Gardner which found such a link.  Also cancer 
researcher Dr Leo Kinlen has published new evidence supporting his 
theory that leukaemia is a virus caused when large numbers of people 
move into an area, i.e. construction workers at major nuclear sites and 
areas used to evacuate children from cities in the Second World War 
supported his previous research.

12.2. Greenpeace take lid off Cap La Hague: A report on radioactive 
discharges and waste production at the Cap La Hague reprocessing 
plant in northern France published by Greenpeace states that the 
plant's annual discharge limit is about three times the total liquid 
discharges from all nuclear reactors world-wide.
© Copyright N-Base/NENIG