Damning Reports on Sellafield

The following reports have been gathered from various sources about the reports by the Health and Safety Executive's Nuclear Installations Inspectorate (NII), published on Friday 18th February 2000 on British Nuclear Fuels and the Sellafield reprocessing plant. The reports concerned (1) The scandal of false quality data for plutonium fuel; (2) A safety audit of the plant; (3) BNFL's failure to deal with high-level waste at Sellafield.

  • Summary of NII report on Sellafield Safety
  • Summary of NII report on MOX plutonium fuel
  • Summary of Events on MOX fuel from NII report
  • Summary of NII report on high-level waste at Sellafield
  • Greenpeace press release
  • British Nuclear Fuels press release
  • Briefing from Cumbrians Opposed to Radioactive Environment
  • Friends of the Earth comments
  • MOX problems spread to Germany - BNFL comments

  • HSE TEAM INSPECTION OF THE CONTROL AND SUPERVISION OF OPERATIONS AT BNFL's SELLAFIELD SITE

    FOREWORD

    This report sets out the findings of a multidisciplinary team inspection
    carried out by HSE into the control and supervision of operations at BNFL's
    site at Sellafield.

    The investigation was carried out under the control of the Deputy Chief
    Inspector of HSE's Nuclear Installations Inspectorate who is responsible for
    regulating safety at BNFL's sites. The inspection was carried out between 6
    and 27 September 1999. HSE's team consisted of 11 nuclear inspectors and 2
    inspectors from its Field Operations Directorate together with
    administrative staff.

    The inspection was requested by the Chief Inspector of Nuclear Installations
    following a series of events at Sellafield where the cause was seen to be
    weaknesses in control and supervision.

    The team found that there were indeed weaknesses in this area and has made
    recommendations to overcome them. BNFL had also recognised shortfalls in the
    company's performance and had introduced initiatives to correct the
    shortfalls.

    The weaknesses found showed that there had been a deterioration in safety
    performance at Sellafield. The recommendations identified in this report are
    those which BNFL needs to implement to fully meet the standards that are
    expected of a nuclear site licensee. Sellafield is not unsafe, but strong
    management action is needed to ensure that it both remains safe into the
    future and that BNFL makes the practicable improvements which can reasonably
    be expected.

    NII has required BNFL to produce a programme for responding within 2 months
    to the recommendations of this report. Progress will be monitored as part of
    NII's normal process of regulation. Should progress be inadequate, NII will
    not hesitate to use its enforcement powers.

    If you have any comments, or would like further information on the issues
    discussed in this report, write to the Chief Inspector at the address below:

    Laurence Williams
    Director of Nuclear Safety and
    HM Chief Inspector of Nuclear Installations
    Health and Safety Executive
    St Peter's House
    Stanley Precinct
    Bootle L20 3LZ


    SUMMARY

    The BNFL Sellafield Site located in Cumbria contains two types of nuclear
    installations. Four Magnox type reactors provide steam and electricity for
    the Sellafield site and supply electricity to the national grid. The
    remainder of the site, comprising several hundred buildings, is associated
    with the reprocessing of spent nuclear fuel and the treatment and storage of
    radioactive wastes. The team inspection described in this report was carried
    out on the facilities associated with reprocessing and waste treatment and
    storage.

    During the first half of 1999, an apparent increase in the number of
    incidents occurring at Sellafield was detected by NII. Investigation of some
    of these events by the NII inspection team for Sellafield indicated that
    inadequacies in BNFL's arrangements for the control and supervision of
    operations appeared to be a significant contributor to the poor safety
    performance. The Chief Inspector of Nuclear Installations therefore decided
    that a team inspection should be carried out to investigate these apparent
    shortcomings in the control and supervision of operations.

    A team comprising 11 NII inspectors and 2 inspectors from HSE's Field
    Operations Directorate was assembled. In selecting the team, care was taken
    to obtain a balance of inspectors with site inspection experience and
    specialist knowledge in the areas to be inspected and also with experience
    of inspection at both Sellafield and other nuclear establishments. In order
    to maximise the time available for inspection on site, planning for the
    inspection and examination of written information from BNFL was carried out
    prior to commencing the on-site inspection activities. The team spent two
    weeks on site in September 1999. Some members of the team also visited
    BNFL's headquarters at Risley. Whilst on site, the team generally operated
    as three groups (focusing on the topics of incidents, control and
    supervision of operations, and staffing and resources), but regrouped where
    appropriate to pursue central issues associated with the management of the
    Sellafield site.

    One Improvement Notice was served during the inspection requiring
    improvements to BNFL's system for controlling risks to persons working at
    heights. On another occasion BNFL voluntarily stopped a plant when serious
    deficiencies were brought to its attention. BNFL has also agreed to
    undertake a systematic assessment of the baseline resource levels it
    requires for undertaking its current activities before any further changes
    are made to its organisational structure.

    The inspection confirmed NII's original concerns about control and
    supervision. BNFL had already recognised a number of the shortcomings
    identified during the course of this HSE team inspection. In particular, it
    has recognised the need to bring about greater integration of the Sellafield
    site under the management of a team with authority to manage operations on
    the site and has begun to take steps to address this. It has also put in
    place a programme of initiatives intended to improve safety in a number of
    areas. Unless there are proactive systems for checking that the required
    standards are being maintained, non-compliances are likely either to go
    undetected, or to have caused significant problems by the time they are
    detected.

    There are three key conclusions from this inspection. The first is that
    there is a lack of a high quality safety management system across the site
    which is compounded by an overly complex management structure. The second is
    that there are insufficient resources to implement even the existing safety
    management system. The third is a lack of an effective independent
    inspection, auditing and review system within BNFL. Without a vigorous
    independent inspection, auditing and review system, HSE does not see how
    BNFL can make acceptable and timely progress in delivering a high quality
    safety management system across the site.

    Return to Top


    An Investigation into the Falsification of Pellet Diameter Data in the MOX
    Demonstration Facility at the BNFL Sellafield Site
    and the Effect of this on the Safety of MOX Fuel in Use

    by The Nuclear Installations Inspectorate of the HSE

    FOREWORD

    This report sets out the findings of the investigation carried out by HSE's
    Nuclear Installations Inspectorate into the falsification of quality
    assurance data associated with the production of MOX nuclear fuel pellets
    manufactured in the MOX Demonstration Facility at Sellafield.

    The investigation was carried out under the control of the Deputy Chief
    Inspector responsible for regulating the safety at BNFL's sites. The
    investigation began shortly after BNFL notified NII of suspected
    falsification on 10 September.

    It is the Executive's view that the report gives a thorough analysis of the
    issues surrounding the falsification of quality assurance data at MDF. It is
    clear that various individuals were engaged in falsification of important
    records but a systematic failure allowed it to happen.

    It has not been possible to establish the motive for this falsification, but
    the poor ergonomic design of this part of the plant and the tedium of the
    job seem to have been contributory factors. The lack of adequate supervision
    has provided the opportunity. Despite this, self-discipline ought to have
    ensured that those involved followed the proper procedures.

    One point worth noting is that in the new Sellafield MOX Plant, currently
    being commissioned, the inspection processes for MOX pellets, rods and
    assemblies are designed to be almost fully automated: this should prevent
    the falsification of data of the kind described in this report.

    There are many lessons to learn, but the MOX Demonstration Facility is shut
    down and will not be allowed to restart until NII is satisfied that the
    recommendations in the report have been implemented.

    If you have any comments, or would like further information on the issues
    discussed in this report, write to the Chief Inspector at the following
    address below:

     
    Laurence Williams
    Director of Nuclear Safety and HM Chief Inspector of Nuclear Installations
    Health & Safety Executive
    St Peter's House
    Stanley Precinct
    Bootle L20 3LZ

    SUMMARY

    The MOX Demonstration Facility (MDF) at BNFL's Sellafield site manufactures
    MOX (mixed oxides of plutonium and uranium) fuel pellets and assembles these
    using various customer supplied components to make complete fuel assemblies
    for use in nuclear power reactors. Each fuel pellet produced passes through
    a fully automated laser micrometer which checks and records the pellet's
    diameter at three points along its length, giving a 100% automatic check on
    all pellets used in a fuel rod. Any undersized or oversized pellets are
    automatically rejected. Those which fall within the specified diametral
    tolerance pass onto the next stage where each undergoes further visual
    checks. As a confirmatory check on diameter and in accordance with the 1%
    Acceptable Quality Level (AQL) criterion set out in BS 6001, a sample of 200
    pellets (approximately 5%) which have passed through both these stages is
    measured for a second time. This quality check is done using a similar
    micrometer, but the sample pellets are presented to the micrometer by
    process workers who type each measured diameter, e.g. 8.195mm, into a
    computer spreadsheet.

    On 20 August 1999 a member of MDF's Quality Control Team identified
    similarities between the secondary pellet diameter data for successive Lots.
    After further investigations, on 10 September 1999 BNFL reported to NII that
    some of these secondary pellet diameter checks on the fuel manufactured for
    a Japanese customer appeared to have been falsified by copying some data
    between spreadsheets.

    The Health and Safety Executive's Nuclear Installations Inspectorate (NII)
    promptly launched an investigation to establish both the extent of the
    falsification and the causes of the event. NII concluded that data had
    indeed been falsified but that this would not affect the safety performance
    of the fuel, given the automated primary diameter check on 100% of the
    pellets used in each fuel rod.

    NII believes the failure to properly carry out the agreed manual checks of
    the pellet diameter to be a contractual issue between BNFL and its customer.
    However, because it also represents a deliberate breach of operating
    procedures the Inspectorate launched an investigation which centred upon:

    1.understanding just what had occurred in MDF and why; 2.whether the fuel
    involved will be safe in use; and 3.what needs to be done to prevent any
    recurrence.

    NII's investigation into possible reasons for the falsification identified
    that although various individuals were at fault, a systematic failure
    allowed it to happen. In a plant with the proper safety culture, the events
    described in this report could not have happened.

    NII commissioned an independent analysis by HSE's statisticians of the
    extent of the falsification. The results of this and further manual checks
    of data by NII showed that the initial investigation by BNFL, carried out
    under severe time pressures was too narrow: there had been a tendency to
    rush to early conclusions which understated the extent of the problem by
    assuming that the falsification was largely confined to one shift.
    Nevertheless BNFL agreed to carry out further, more detailed investigations
    and, following discussions with NII, has taken steps to address the
    contributory factors to this incident which the Company and the Inspectorate
    have identified.

    NII is satisfied that in spite of the falsification of the quality assurance
    related data, the totality of the fuel manufacturing quality checks are such
    that the MOX fuel produced for Japan will be safe in use. With regard to
    MDF, the plant is shut down and will not be allowed to restart until NII is
    satisfied that the recommendations outlined in this report have been
    implemented to ensure, inter alia, that the deficiencies found in the
    quality checking process have been rectified, the management of the plant
    has been improved and plant operators have been either replaced or retrained
    to bring the safety culture in the plant up to the standard NII requires for
    a nuclear installation.

    CONCLUSIONS

    103. The events at MDF which have been revealed in the course of this
    investigation could not have occurred had there been a proper safety culture
    within this plant. It is clear that some process workers falsified records
    of the diameter of fuel pellets taken for QA sampling. One example of
    falsification has been found dating back to 1996. There can be no excuse for
    process workers not following procedures and deliberately falsifying records
    to avoid doing a tedious task. These people need to be identified and
    disciplined. However, the management on the plant allowed this to happen,
    and since it had been going on for over three years, must share
    responsibility.

    104. Before NII will allow the restart of MDF, BNFL will need to address all
    the recommendations in the report to the Inspectorate's satisfaction.

    Return to Top


    Summary of Events

    On 20 August 1999 a member of the Quality Control Team in B33 MOX Demonstration Facility
    (MDF) identified a similarity between mean pellet fuel diameter measurements reported on the QC
    release certificates for the secondary sample checks of two successive Lots. These were discussed by
    the QC Team in MDF on 23 August. Plant management was informed of these similarities on

    25 August and the Shift Team Leaders were asked to pay particular attention to inspection of pellets
    pending completion of QC release.

    On 31 August BNFL's analysis of data for several Lots showed many of the mean pellet diameter
    values in successive Lots to be the same, and the MDF QC management initiated a computerised
    analysis of the data. Discussion with individuals concerned began on 1 September 1999. On 6
    September the MOX Senior Team was informed that some falsification of data may have occurred.

    On 3 September a process worker in MDF admitted deliberate falsification, and a second process
    worker said that he was aware falsification was taking place. On 9 September the QC management updated the MDF Operations management on the results of the preliminary investigation. Over 9/10 September Trade Union officials met plant management with individuals concerned to try to understand the extent of the problem.

    On 10 September the Independent Newspaper indicated to BNFL its intention to publish an article in

    the newspaper concerning the fact that BNFL inspectors had falsified QC data on MOX pellet
    diameter. The article was eventually published on 14 September.

    On 10 September Mitsubishi Heavy Industries (the fuel vendor to Kansai) and NII were informed of
    the situation. NII maintained contact with BNFL thereafter throughout the weekend until the beginning
    of its on-site investigation. BNFL reported to NII that on 12 September 1999 it had found 11 Lots with
    falsified data and 9 "unusual" Lots.

    12 September: NII obtained BNFL's agreement not to restart production until NII had been notified.

    NII was told that on 14 September the BNFL QC Team reported a further five sets of falsified data, and one further set of falsified data a day later. On 14 September NII began its on-site investigation into the incident.

    14-16 September: Visit to the MDF plant by NII Site Inspector and NII Management to begin on-site
    investigation into the event. This included some interviews.

    On 16 September BNFL reported four further sets of falsified data and one additional unusual dataset
    giving a total of 22 falsified datasets and 10 unusual datasets. On 16 September MDF Operations
    Manager reported that BNFL believed that falsification of data had been undertaken principally by one
    of the five shift teams.

    20-21 September: Visit to plant by NII Site Inspector and NII Senior Management. This included a
    plant inspection and meeting with officials from the Ministry of International Trade and Industry
    (MITI), Japan. NII told MITI that it would be carrying out a thorough independent analysis of the pellet
    diameter data for Kansai.

    21 September: NII wrote to the Japanese Embassy in London in response to a letter the previous day from the Economic Counsellor. The letter explained that it would "take some time, possibly several weeks, to check all of the data relating to the fuel which [was] currently en route to Japan". The letter also said that NII understood that BNFL had "already told the Japanese team visiting Sellafield that one Lot of MOX fuel pellets whose secondary sample checks on diameter show "unusual" results has been used in the manufacture of two fuel assemblies [then] currently en route to Fukui".

    On 22 September at a meeting at NII's offices in Bootle, BNFL reported that its continuing
    investigation had concluded that there were 22 falsified data Lots and one unusual data Lot. The other
    nine 'unusual Lots' were eliminated by BNFL. All pellet Lots for which falsified datasets had been

    reported had been used to produce fuel rods and assemblies for Takahama 3, and were still at
    Sellafield. The pellets for an unusual Lot had been used to produce fuel rods in two of the eight fuel
    assemblies for Takahama 4, which at that time were in the process of being transported to Japan.

    22 September: HSE's independent statistical analysis of the pellet diameter data for Kansai was
    initiated.

    28-29 September: Visit to plant by NII Site Inspector to conduct interviews with the Shift Team
    Leaders (STLs), Shift Team Managers (STMs) and the Head of MDF Operations.

    8 October: Visit to plant by NII Quality Assurance (QA) Specialist to investigate QA aspects of the event.

    12-13 October: Visit to plant by NII Site Inspector and Human Factors Specialist to discuss ergonomic
    aspects of the event.

    25-26 October: Visit to plant by NII Site Inspector to witness three separate sets of dual 5% secondary
    diameter checks.

    29 October: The statistical analysis by HSE's EMSU of the data was completed.

    3 November: An update provided by BNFL reported 22 falsified data Lots, one Lot having some
    similarities with a previous Lot, one Lot having greater than normal number of pellets with three
    identical diameters (ie cylindrical), and one Lot having a greater than normal number of identical pellets.

    8 November: BNFL was informed that it would have to produce a safety case and seek NII's
    agreement before it could restart MDF. NII wrote again to the Japanese Embassy confirming that
    "two of the assemblies containing pellets with suspect data are in Japan." A copy of this letter was
    placed in the House of Commons Library.

    10 November: Visit to plant by NII Site Inspector and an Inspector from the Radioactive Materials
    Transport Division of the Department of Environment, Transport and Regions (DETR) to discuss
    BNFL countermeasures to prevent recurrence of the event.

    11 November: A meeting took place between HSE and BNFL to discuss work necessary before MDF
    is permitted to restart.

    17 November: A meeting took place between HSE (NII and EMSU) and BNFL to discuss the findings
    of HSE's statistical analysis of the secondary pellet diameter data. On the same day NII and BNFL
    met to discuss BNFL's proposals for a safety case for the restart of operation in MDF.

    23 November: Visit to plant by NII Site Inspector to investigate ergonomics aspects of the event.

    8-10 December: Visit to plant by NII Site Inspector and Human Factors specialist to undertake a
    restart readiness inspection.

    13 and 14 December: Meeting between NII and MITI officials to explain the results of HSE's
    statistical analysis. NII confirmed the facts set out in earlier letters to the Japanese Embassy ie. that
    two of the assemblies (MKP 005 and 006) in Japan contain pellets believed to have suspect data. HSE staff went to some lengths to explain that although the 8 November letter had used the word "suspect"
    in relation to these assemblies, HSE considered that there was a vanishingly small probability of these
    results [for Lots P783 and P824] having occurred by chance.

    15 December: That evening BNFL reported to NII that following further investigation, data for a
    further Lot, P814, had been found to be copied from a previous lot.

    16 December: Following the discovery by BNFL of the additional falsified Lot, P814, NII asked for a further meeting with MITI which was held the same day. NII confirmed to MITI that P814 had been
    falsified, and that this now meant that two further assemblies in Japan were considered to be affected.
    Taken together with those assemblies identified previously, this now meant that a total of four
    assemblies (MKP 005, 006, 007, and 008) out of the eight assemblies currently in Japan contained
    pellets whose secondary diameter data was considered to have been falsified.

    19 December: Visit to MDF by the Chief Inspector for a plant inspection.

    20 December: BNFL Senior Management met with NII Senior Management at Bootle to discuss the
    improvements which NII require to be implemented before permission to restart would be granted.

    21 December: NII wrote to BNFL listing a number of areas for BNFL to address to NII's satisfaction before agreement to restart would be granted.

    22 December: NII wrote to BNFL specifying under the nuclear site licence, that BNFL should
    demonstrate to its Nuclear Safety Committee how it has satisfied itself that the lessons learned from
    the MDF event will be disseminated to the rest of the site.

    11 January 2000: NII met with BNFL to discuss the process which had been used to identify Lot P814
    as containing falsified fuel pellet diameter data.

    Return to Top


    NII report on High-Level Waste at Sellafield

    SUMMARY

    The storage of liquid High Level Waste (HLW) that results from the reprocessing of irradiated nuclear fuel, has at various
    times been given a high profile by those concerned about the safety of operations at the Sellafield site of British Nuclear
    Fuels plc (BNFL).

    This report provides an update of the various issues raised in the NII's last report on the subject ("Safety of the
    storage of liquid High Level Waste at BNFL Sellafield") produced in November 1995, summarises the latest NII
    assessment of the B215 safety case and details progress against the key safety requirement in the 1995 report for BNFL
    to reduce the stocks of liquid HLW to a buffer volume by around 2015. NII believes that there has to be a
    demonstrable reduction in potential hazard (and hence risk) by reducing the amount of HLW stored as Highly Active
    Liquor (HAL) and that the around 2015 date must therefore be achieved, as any shortfall will be publicly unacceptable.

    The current 1994 safety case together with the additional information provided to NII in response to its issues, has
    enabled the Inspectorate to make the judgement that the current and future operations of B215 are acceptably safe.
    NII's assessment of the BNFL safety case identified concerns that the important engineering justification of the
    B275 structures and systems was not presented in enough detail. There was too much emphasis on probabilistic
    analysis in which numerical results were being used somewhat rigidly to make, rather than inform, decisions on whether
    further work was needed. In addition, the analysis did not cover the full range of fault sequences.

    BNFL is currently carrying out a safety case improvement programme to redress the balance between engineering
    justification and risk analysis in its safety cases. The safety case for B215 is one of the early cases to be reviewed and
    revised as part of this programme and a new safety case has just been submitted at the time of writing. It is intended that
    an addendum to this report will be published in about a year's time when NII has assessed the revised safety case

    The principal safety systems for B215 are those that maintain cooling and containment of the stored HAL.

    Maintaining the integrity of cooling of the stored HAL is fundamental to the safety case. Although the HASTs have shown
    some failures of cooling coils due to corrosion, NII has assessed BNFL's strategy for dealing with the problem and
    is satisfied that sufficient cooling capability is, and will continue to be available. BNFL has upgraded the
    cooling water pipework external to the HASTs, which adds to the system's reliability.

    NII has also assessed the BNFL containment integrity arguments for the Highly Active Storage Tanks HASTs).
    In respect of the ongoing ageing processes, primarily associated with corrosion, NII is satisfied that BNFL
    understands and is controlling the mechanisms that could threaten the containment integrity. BNFL is currently
    implementing a project (completion date 2000) to improve the HAST off-gas treatment systems that will further
    reduce aerial discharges to the environment from the plant. BNFL has also completed additional seismic
    damage assessments of B215 and implemented a programme of reasonably practicable improvements to increase
    the plant's resistance to earthquake damage.

    In response to issues on fire and explosion raised by NII, BNFL has carried out detailed analyses of the plant
    and laboratory scale experimental work to show that adequate controls are in place to safeguard the plant from the
    possible build-up of hydrogen and "Red Oil".

    The declared position of NII and BNFL is that the HASTs should be emptied to a buffer stock and the HAL converted to a
    solid form by around 2015. NII is monitoring BNFL's progress against this intent through reviewing actual
    performance and predictions made using modelling techniques. Changes to the BNFL fuel reprocessing business, that
    affect HAL arisings, are also accounted for in the NII assessment process.

    NII is currently in the process of agreeing with BNFL a number of HAL limiting stock reduction curves against a
    set of monitoring parameters together with a number of programme milestones, against which the HAST emptying policy
    to a buffer stock will be regularly reviewed. NII intends to monitor BNFL's required progress at about 24 month
    intervals and if this falls short of what was agreed will, using regulatory powers if necessary, require BNFL to take
    actions, including reducing HAL arisings, to correct the situation within an agreed period of time.

    Key to this process is agreeing the buffer stock to which the tanks will be emptied and which is necessary to allow control
    of the feed to the vitrification process. BNFL has accepted an NII recommendation to conduct a full study
    of options in order to agree the minimum buffer stocks. The objective of this study is the reduction of risk (harm potential) so far as is reasonably practicable as required by the HSAW Act 1974. It is NII intention to publish a further addendum to this report in about 12 to18 months when progress has been made with these studies.

    The performance of the Waste Vitrification Plant (WVP) is a fundamental part of the process to
    convert HAL to a solid form. WVP continues to experience operational difficulties with respect to achieving the
    desired production rates, and the building of the third WVP process line is currently running late to the original
    programme.

    From the assessment of the data presented by BNFL on future HAL arisings and on the basis of the current
    vitrification plant performance, NII remains to be convinced that BNFL will achieve the aim to reduce the stocks of
    HAL to a buffer stock by 2015, unless:

    (1) there is a significant increase in the throughput of the existing vitrification lines, and

    (2) there is no further slippage in the third vitrification line coming on-stream, and

    (3)the third fine meets its planned throughput targets,

    Failure to achieve the above would leave BNFL with the following options to rectify the situation:

    * Voluntarily reduce THORP throughput

    * Close some Magnox generation capacity earlier than planned to reduce Magnox HAL arisings

    * Construct additional vitrification plant capacity (Line 4).

    The choice of which option to adopt would be a matter for the company and could involve some combination of the
    above.

    NII has made a number of recommendations in this report that need to be addressed by BNFL to ensure that
    future B215 operations will continue to meet the requirement to control and reduce risks to as low as reasonably
    practicable (ALARP). The recommendations are made in the areas of plant and operations improvement,
    safety case improvement, and the policy to reduce the quantity of HAL to a buffer stock by 2015. The recommendations in
    this report have been forwarded to BNFL. It has recently responded to the first 17 recommendations. For the
    majority of these recommendations BNFL has referred NII to their recently revised case, referred to as a Continued
    Operations Safety Report, delivered to NII on 29.9.99. NII acknowledges that BNFL is currently carrying out work
    against most of the recommendations, and this report serves to highlight the significance NII attaches to the
    improvements. NII will be progressing with BNFL the necessary follow-up work to a satisfactory conclusion as part of its
    normal regulatory duties conducted under the site licensing arrangements.

    This review has shown that there is little or no slack in BNFL's programme of vitrification if the reduction in HALL to a
    buffer stock, by the 2015 date, is to be maintained. NII notes that it has recently been repeated within the House of Lords
    Select Committee on Science and Technology (Ref 12) "that it would take until about 2015 to vitrify all the HLW in
    stock." HSE will not hesitate to use its regulatory powers to ensure the HAL stock reduction, when agreed, is
    achieved.

    Return to Top


    Greenpeace demands shutdown not Modification of Mox NuclearFuel

    Production After Regulator Details Safety Data

    Falsification Continued for Four Years

    LONDON, Feb 18, 2000 – The production of mixed uranium plutonium oxide (MOX)
    fuel by British Nuclear Fuels Ltd (BNFL) at Sellafield in north-western England must
    be scrapped by the British government following the release of a damning report by
    the nuclear regulatory body, Greenpeace said today.

    The Nuclear Installations Inspectorate (NII) report released today revealed that the
    falsification of safety data for MOX fuel had gone on since 1996 and involved British
    Nuclear Fuels Ltd (BNFL) major overseas clients, Japan and Switzerland. “The
    appalling mismanagement of BNFL has destroyed not only the trust of their
    Japanese clients, crucial to their survival, but also public faith in the British regulatory
    system,” said Greenpeace International nuclear campaigner Shaun Burnie. “If BNFL
    was not a taxpayer funded enterprise they would now be out of business.”

    However BNFL and the NII continue to insist that the MOX fuel is safe to use, despite
    the safety data falsification. This is despite the revelation last December that MOX
    fuel produced by BNFL and loaded into a reactor in Switzerland, ruptured, leaked
    radiation and had to be removed. MOX fuel, due to the presence of plutonium, is
    widely considered less safe than conventional uranium fuel. Investigations last
    September into BNFL MOX quality control standards concluded that it was practicably
    impossible to assure the quality and therefore the safety of MOX fuel produced by
    BNFL.(1)

    “For the British nuclear regulator to continue to maintain that the MOX fuel is safe to
    use in Japanese reactors, despite the safety data falsification, raises serious doubts
    about its credibility,“ said Burnie. “The Japanese public are rightly sceptical of the
    safety claims for the MOX fuel, which has led the Japanese government to demand
    its return to the UK, this report will do nothing to reassure them.”

    Greenpeace warned that the recommendations made by the NII for ‘modifications’ to
    MOX production at Sellafield and retraining of staff will not address the industry’s
    fundamental problems. “The British and Japanese governments must finally end the
    folly of MOX production which cannot be justified on safety, economic or
    environmental grounds and also poses a major nuclear weapons proliferation threat
    in the volatile north-east Asian region. They must stop any further reprocessing and
    abandon plans to open the doomed Sellafield MOX Plant,” said Burnie.

    Currently the Nuclear Energy Agency estimates that making MOX costs 3 to 5 times
    the cost of making uranium fuel, the standard fuel for the majority of nuclear reactors
    around the world. The Sellafield nuclear facility discharges 3.3 billion litres of nuclear
    waste each year in the Irish Sea.

    The MOX plant at the centre of this scandal, the MOX Demonstration Facility (MDF),
    received a £100 million upgrade in the early 1990’s, while at the same time, BNFL
    proceeded with construction of the £300 million Sellafield MOX Plant. Ready for
    operation in June 1997, the plant still remains idle, with the UK government
    unprepared to open a plant that has almost no commercial contracts for MOX fuel
    with foreign electrical utilities and British nuclear utilities have no plans to use MOX.

    The BNFL/Japan MOX falsification scandal only became public after the Independent
    newspaper revealed details last September. In the following three months, BNFL,
    Kansai Electric, and the Japanese Ministry of Trade and Industry, MITI, continued to
    deny that the scandal effected plutonium fuel newly arrived in Japan from the UK. The
    fuel was due to be loaded into the Takahama reactor in Japan at the end of the year,
    however BNFL was forced to admit that the MOX fuel contained ‘suspect’ quality
    control data.

    Return to Top


    BNFL Press Release

    18 February 2000 - BNFL outlines forward action plan for

    MOX fuel and Sellafield

    BNFL today published its review of the secondary quality data problem
    discovered within the MOX Demonstration Facility (MDF) at Sellafield. The
    review involved the senior non-Executive director and Chairman of BNFL's
    audit committee, Mr John Roques. It details how the falsification occurred
    and the remedial measures planned to ensure that such an event could not
    happen again. A total of twenty two actions are grouped under the following
    areas:

    *Strengthening of supervision and leadership*Establishing a manufacturing
    ethos and attitude*Improving the effectiveness of the Quality
    Assurance/Quality Control compliance system*Re-establishing customer
    confidence in BNFL's MOX fuel*Re-establishing Government and regulatory
    confidence in BNFL's MOX fuel*Reviewing and revising our forward business
    strategy

    The Health and Safety Executive (HSE) has also published its own report on
    the events in MDF. BNFL has taken HSE's recommendations on board and is
    already implementing an action plan which will systematically address them.
    Indeed, the HSE's first recommendation that the recording of the secondary
    quality data should be automated has already been incorporated within the
    Company's immediate plans.

    The HSE's report also systematically addresses the question of whether the
    data falsification could have affected the safety of the fuel. HSE's view is
    that from a technical viewpoint, the extensive checks performed at all
    stages of fuel production - both before and after the stage at which some
    falsification occurred - mean that the fuel would be safe in use.

    BNFL Chief Executive John Taylor and Chris Loughlin, the BNFL Board director
    responsible for MOX business are this week in Japan meeting with customers.

    Commenting on the review published today, John Taylor said: "We deeply
    regret these events and the problems that they have caused for our
    customers. We now need to get on with implementing the action plan and
    restoring our credibility."

    A further two reports have also been published today by HSE relating to a
    team inspection of the Sellafield site conducted in September last year and
    a review of progress in reducing quantities of liquid high level waste
    stored at Sellafield.

    Commenting on all of the reports which have been issued today, John Taylor
    said: "Taken together the four reports published today provide a valuable
    input to the change programme we are implementing throughout the Company.
    The reports acknowledge that we have made a good start and they also point
    out areas where we still have much to do. I look forward to working with our
    customers and our regulators to achieve our vision of world class standards
    in safety and plant operations."

    HSE NII Team Inspection

    BNFL has a Sellafield site action plan underway in order to address many of
    the recommendations in this report and the Company will continue to work
    with the regulator in reviewing progress against an agreed plan which
    addresses all of the recommendations. Taken as a whole, this examination of
    the management, control and supervision of operations, staffing and
    incidents should give reassurance to BNFL's employees, the local community,
    customers and the general public that the site is being run in a safe and
    secure manner.

    Commenting on this report, Brian Watson, Head of the Sellafield Site, said:
    "We have to remember that nobody is saying that Sellafield is unsafe. Safety
    is, and will always be our number one priority and the independent rigour
    which the HSE applies to our own standards is a key element in our
    continuing drive to achieve world class safety."

    BNFL will use the findings of the Team Inspection to build upon the safety
    improvements already achieved at Sellafield. These include:

    *A three-fold reduction in the average employee radiation dose between 1988
    and 1998 to the point where today, the average Sellafield worker receives an
    occupational dose which is nearly half that of the average airline crew.
    *Radioactive discharges to sea are now less than 1% of their peak levels in
    the 1970s, due to an investment of more than £2 billion in waste management
    and effluent treatment facilities over the last ten years.*The number of
    radiological incidents at Sellafield has remained broadly the same over the
    last ten years, against the background of an increasing workload and scope
    of activities at Sellafield including decommissioning and clean up.*Last
    year, the Sellafield site was awarded a total of seventeen RoSPA Awards,
    whilst the number of lost time accidents at Sellafield has reduced ten-fold
    over the last ten years.*In September last year BNFL, in partnership with
    the trade unions, successfully introduced a new employee contract across the
    Sellafield site and the Company. The contract is widely recognised as being
    amongst the most advanced in the world. *Specifically, the new contract
    encourages more flexible working and will be a key element in the whole site
    pulling together to achieve the operational changes needed.

    Progress in reducing high level waste

    BNFL welcomes the HSE's independent verification of safety at the liquid
    high level waste storage facility and their continuing view that it is
    acceptably safe. The report makes a total of twenty two recommendations, of
    which the first seventeen have already been addressed as part of the revised
    safety case which was delivered to HSE, as agreed in September 1999. The
    remaining five recommendations relate to longer term reviews and studies of
    an ongoing nature which will be progressed in the coming months and years.

    BNFL notes the HSE's comments on progress in reducing the amount of liquid
    waste in storage and remains confident that the target date of 2015 for the
    vitrification of all but buffer levels of liquid waste will be met. A number
    of operating difficulties during the early years of the vitrification plant
    delayed progress in working through this backlog, however these have now
    been resolved and plant throughput has improved in recent years. The Company
    is now commissioning a new vitrification line which will further increase
    throughput. Lessons learnt in operating the original two lines have been
    incorporated into the third line, which is scheduled to start operations
    later this year.

    Return to Top


    Briefing from Cumbrians Opposed to a Radioactive Environment

    98 Church St, Barrow, Cumbria LA14 2HJ.
    Tel 01229 833851. Fax 01229 812239
    e.mail: info@core.furness.co.uk

    Subject: Sellafield Update: MOX, Site Safety, High Level Waste, Prosecution.

    Friday 18th February 2000 must be recorded as the blackest day in BNFL's 30 year chequered history, with the publication of three damning reports by the Health & Safety Executive's Nuclear Installations Inspectorate. Publication of the reports, coinciding with BNFL executives' last-ditch attempts to patch up the company's shattered MOX relationship with Japanese customers, has brought combined criticism of the Company from all quarters including the UK Government.

    MOX falsification scandal:

    NII's report, published one week after their Director of Nuclear Safety had been to Japan to explain the findings to the Japanese Government and Industry, concludes that a systematic management failure allowed individuals to falsify quality assurance records for MOX pellet measurements. Their investigation at the small MOX Demonstration Facility (MDF) at Sellafield found that 31 Lots of MOX pellets (around 4000 pellets per Lot) had been subject of data falsification since 1996. The affected Lots included those made up into fuel assemblies and already shipped to Japan in 1999. Earlier shipments to Switzerland (Beznau) and Germany (Unterweser) were also affected.

    The investigation by the NII considered three possible types of data falsification. 1. Copying a whole spreadsheet and replacing some data entries, 2. Copying whole rows of three data entries within a spreadsheet (the three diameter readings for one pellet) and 3. Other manipulation and invention. A majority of the falsifications found came under category 1 and related to the secondary manual check carried out by workers on a randomly selected 200 pellets from each Lot of 4000.

    NII were unable to establish a motive for the falsification, but suggested a combination of poor ergonomic design of the plant, the tedium of the job or the ease with which the computer data logging system could be manipulated. Currently closed down, MDF will not be permitted by NII to restart production until 'deficiencies found in the quality checking process have been rectified, the management of the plant improved and the operators either replaced or retrained to bring the safety culture in the plant up to the standards the Health & Safety Executive requires for a nuclear installation'.

    Since MDF started operating in 1993, 6 consignments of MOX fuel (a total of 36 assemblies) have been delivered to overseas customers. Of these 6 consignments, four have now been found to have contained either falsified quality assurance data or faulty fuel. In 1998, faulty MOX fuel rods were returned to Sellafield by the operators of the Swiss Beznau power station.

    BNFL's poor management of MDF and their dishonesty about data falsification has been roundly condemned by UK Government which has already had to send a high level team of Department of Trade and Industry (DTI) officials to Japan to apologise to their counterparts. Energy Minister Helen Liddell has described BNFL's behaviour as completely unacceptable and has called for a 'root and branch' review of BNFL management. DTI's Secretary of State Stephen Byers has highlighted funadamental flaws in BNFL management. Calls for senior management heads to roll by both Liddell and Byers have been widely echoed in all strands of the British media. Sellafield's local MP Jack Cunningham has called for sackings up to Boardroom level.

    Five shopfloor workers have been dismissed by BNFL since the MOX scandal came to light last September. The three workers originally sacked have lodged a claim for unfair dismissal with an Industrial Tribunal. The other two workers are still persuing their case through the company's internal disciplinary system. Represented by the GMB trades union, all five workers consider they have been scapegoated by BNFL, and the NII report's crticism of systematic management failure has brought renewed calls from workers and others that some managers and even members of the BNFL Board, including the Chief Executive John Taylor, should now be sacked.

    BNFL's future MOX business now hangs in the balance as the Japanese Government and Industry decide whether or not to continue dealing with BNFL as a supplier of MOX. This may take many months and is likely to delay even further any UK Government's decision on BNFL's new Sellafield MOX Plant (SMP), already delayed for three years. Ministers' uncertainties as to the viability of SMP will have deepened as a result of the current fiasco, and they will be assessing the likely knock-on effect on existing customers in Germany and Switzerland . The ultimate humiliation for BNFL will be the Japanese Government's insistence that the MOX fuel shipped to Japan last year, and subject to falsification, be returned to Sellafield at BNFL's cost. Such a shipment, requiring prior approval of the United States and others, would have to be undertaken by BNFL's converted gunboats against a tide of international condemnation.

    Sellafield Safety Audit - NII team Inspection.


    Following an increase in accidents and events at Sellafield in early 1999, NII inspectors carried out a three week inspection of Sellafield last September (see CORE Briefing 14/99). Their findings were published last Friday along with their MOX investigation report.

    In their main conclusions, NII highlights the lack of a high quality safety management system on the site, and also the lack of sufficient resources to implement such a system. NII was also highly critical of the standard of safety documentation at the plant and, as a result of efforts to make the company attractive for privatisation, the fact that managers were having to divert as much as 50% of their time from operational matters - adversely affecting plant safety.

    Making 28 recommendations to improve safety throughput the site and at all levels of the workforce, NII have given BNFL 2 months in which to produce a programme of response to the recommendations.. Laurence Williams, for NII, has said that control and supervision of operations at Sellafield is of paramount importance and NII will use its regulatory powers to ensure that the company implements the report's recommendations to reverse the decline in safety performance at the site. Should progress be inadequate, NII would not hesitate to use its enforcement powers, including closing down the site.

    High Level Liquid Wastes at Sellafield.


    In the third report to have been published last Friday, NII has published its updated safety review of BNFL's management of HLW at Sellafield. NII's first Review was published in 1995. Inspectors remain critical of the apparent inability by BNFL to treat the backlog of High Level Wastes, stored in a number of tanks, which result from Sellafield's reprocessing operations (see CORE Briefing 13/99).

    The wastes are accumulating faster than BNFL is able to deal with them at Sellafield's Vitrification Plant, where the liquid is turned into glass. There is currently around 1300 cubic metres of HLW at Sellafield.The Vitrification Plant currently has two operating production lines, both of which have significantly underperformed. A third production line is due to open at the end of this year and with all three lines operating BNFL plans to catch up with the backlog of which the NII is so critical. Despite previous threats from the NII, BNFL's programme has remained behind target and NII has again threatened that they will stop reprocessing operations at Sellafield if BNFL's vitrification performance does not improve.

    NII are requiring BNFL to reduce stocks of liquid HLW to a 'buffer' quantity - the minimum required for safe and efficient operation. This reduction is to be completed by around 2015 .

    Prosecution.

    As a final blow on the blackest of Fridays for BNFL, NII announced that the Company was to be prosecuted for an incident at Sellafield in March last year when two workers received burns following a spill of nitric acid in Sellafield's newly built Solvent Treatment Plant (see CORE Briefing 5/99). The œ60m plant treats the backlog of acid used historically in reprocessing operations. The prosecution is expected to take place this Spring.

    Return to Top


    BNFL can't be trusted say Friends of the Earth

    Commenting on the scandal over the falsification of plutonium data by
    BNFL, Mark Johnson, Energy campaigner at Friends of the Earth said:

    "This scandal leaves the business case for the new large-scale MOX plant
    in tatters. John Prescott now has no option but to reject BNFL's application to
    operate the plant. It would be foolish, and probably illegal, for the
    Deputy PM to give the go-ahead after this shameful episode.

    This whole affair shows, once again, that BNFL cannot be trusted and
    that the economic and environmental madness of reprocessing must not be
    allowed to continue.

    The nuclear industry does have a future, but this lies with clean-up and
    decommissioning. This will provide long-term jobs and safeguard the
    environment for future generations as well as securing a stake for
    Britain in dealing with the mess that the nuclear industry has created
    worldwide."

    For more information see www.foe-scotland.org.uk/

    Return to Top


    MOX problems also in Germany

    There have been calls for the Nuclear Installations Inspectorate to release all information and data relating to
    the falsification of safety data of nuclear fuel by British Nuclear Fuels Ltd (BNFL) which was sent to Germany.

    Greenpeace understand that 4 assemblies of plutonium uranium oxide (MOX) fuel are loaded in the Unterweser reactor, in northern Germany (the only German plant using BNFL plutonium fuel). The fuel was shipped on the
    roll-on-roll off cargo vessel, Arneb in October 1996. It is estimated to contain around 100-120kg of plutonium, plus approximately 2 tons of uranium.

    The disclosure that BNFL nuclear fuel safety scandal extends to Germany follows recent British government answers to parliamentary questions that revealed that nuclear fuel with falsified safety data had also been sent
    to Switzerland in 1997 where it was loaded into the Beznau nuclear reactor. In separate incident another batch of BNFL MOX ruptured in the same reactor in 1997. The operator removed the fuel after detecting abnormal levels of radiation.

    The confirmation of the falsification of MOX fuel sent to Germany was contained in a reference in the UK government's report on MOX falsification released Friday, that MOX fuel produced in 1996 contained falsified quality control data(1).

    BNFL only produced MOX fuel for Germany in 1996. However the report failed to provide details of MOX fuel
    provided to Switzerland and Germany, instead it concentrated on fuel manufactured for Japanese client, Kansai Electric.

    All three client countries of BNFL’s MOX Demonstration Facility - Japan, Germany and Switzerland - have received plutonium fuel that is not safe to use due to vital quality control checks having been missed. Kansai Electric has abandoned plans to use the 8 fuel assemblies now in Japan, and is demanding their return to Britain.

    “This is further damning evidence against BNFL’s plutonium business, as well as the UK and German authorities”, said Simon Boxer of Greenpeace International. “For almost four months BNFL denied that that plutonium fuel shipped to Japan had been falsified, the UK regulators have so far failed to provide any details on either Swiss or German falsification. The
    German authorities have apparently made insufficient checks, telling Greenpeace only last week that everything was normal,” said Boxer.

    “All of the relevant quality control data for MOX produced for Germany, and Switzerland, must be publicly released so that it can be independently scrutinized,” said Boxer. “The nuclear industry and the regulators cannot be trusted to do a thorough job.”

    Greenpeace contacted the German authorities last week in Lower Saxony which oversee the Unterweser reactor. They stated that they had been informed by the reactor's operator, electrical utility PreussenElektra, about the data falsification problem last autumn. The Lower Saxony authorities stated to Greenpeace that they had looked at the fuel data and found no anomalies.

    Before closing its own MOX fuel production plants, Germany produced MOX fuel at the small Hanau plant which was closed in 1995 after a series of accidents. A new 1.1 billion German marks MOX plant at the same site never became operational due to environmental opposition.

    BNFL Press Release - BNFL MOX Fuel In Germany

    21st February 2000

    Since the incidence of falsification of secondary pellet diameter measurements in Japanese fuel came to light, BNFL has
    conducted an investigation of all quality data relating to German fuel. The customer has seen the results of this investigation and
    done his own audit. Both BNFL and our German customer have concluded that the fuel manufactured for Germany meets the
    specification and this is borne out by the fact that it has been performing satisfactorily in the reactor for nearly three years.

    One case of 'falsification' was found, which occurred when an individual inadvertently deleted a set of data, and copied a set of
    previous data to save repeating the work.

    BNFL has carried out further checks on data for MOX fuel supplied to Germany. These checks applied the same methodology which brought to light the additional falsifications in the Japanese fuel. This additional analysis has revealed no further evidence of falsification, apart from the incident mentioned above. BNFL's investigation showed that the secondary diameter measurements for this pellet lot had been properly taken and the lot met the acceptance standard.

    Media Affairs
    21 February 2000.

    Return to Top